Nieuwsbericht | Datum: 06-12-2017


BAM revises outlook following cost overrun at sea lock IJmuiden




Based on the latest available information, Royal BAM Group nv expects a considerable project loss in 2017 on the sea lock IJmuiden.

Rijkswaterstaat awarded the OpenIJ consortium the contract to design, construct, finance and maintain a new sea lock at IJmuiden in mid-2015. The contract value is approximately €600 million. Construction activities are carried out by a 50/50 joint venture between BAM and VolkerWessels.

The loss mainly relates to the redesign of the two caissons (the construction holding the lock doors) to prevent torsion and cracking during immersion. The new design specified reinforced caissons and heavy temporary structures. Recent implementation works revealed significantly higher costs for specialist materials and equipment and personnel over the prolonged construction period. For BAM, this will lead to an estimated additional project loss of around €55 million in the fourth quarter 2017. As a consequence, BAM expects an adjusted result before tax for the full year 2017 which will be substantially lower compared to 2016.

BAM CEO Rob van Wingerden commented:
'We are very disappointed with this significant cost overrun. We are working with our joint venture partner in close consultation with the client to deliver this important project for the Amsterdam region. Despite this setback we remain confident we are on the right track to realise our strategic ambitions.'


Deel dit artikel:                   





Definitieve keuze voor herbouw Sluis II Wilhelminakanaal Tilburg
Nieuwsbericht
VolkerWessels reports setback for OpenIJ construction
Nieuwsbericht
BAM revises outlook following cost overrun at sea lock IJmuiden
Nieuwsbericht
Totale range zeespiegelstijging groter dan gedacht
Nieuwsbericht
Nederland herkozen in raad van internationale maritieme organisatie IMO
Nieuwsbericht
Smart Shipping Challenge: stap naar slimme en veilige binnenvaart
Nieuwsbericht
Terugblik Waterbouwdag 2017
Weblogposting
Veranderend zand: onderzoek naar invloed van mensen op strandecologie
Nieuwsbericht
Quickscan naar duurzaamheid in dijkversterkingsprojecten
Nieuwsbericht
Infra Relatiedagen 2018: Komt u ook op de vakbeurs waar de complete infrabranche samenkomt?
Weblogposting
Waterinnovatieprijs 2017 uitgereikt
Nieuwsbericht
Water in de Openbare Ruimte 2017: Dank voor de waardering!
Weblogposting
Eerste Watertrucks weldra op kleine waterwegen
Nieuwsbericht
Arcadis en Sweco in raamovereenkomst Sterke Lekdijk
Nieuwsbericht
Geotechniekdag 2017
Weblogposting
Start ontwikkeling NTA voor IFD-bouw beweegbare bruggen
Nieuwsbericht
Aangepaste aanbestedingsdocumenten voor Design & Construct-contracten
Nieuwsbericht
Steun op VN klimaattop voor nieuw in Nederland gevestigd klimaatcentrum
Nieuwsbericht
Eerste schop in de grond voor bouw Nieuwe Sluis Terneuzen
Nieuwsbericht
Viering hoogwaterveiligheid Grensmaas
Nieuwsbericht
RIONED vraagt Input voor ontwikkeling stresstest regenwater
Nieuwsbericht
Nominaties RIONEDinnovatieprijs 2018
Nieuwsbericht
Water in de Openbare Ruimte 2017: Oplossingen om uw stad 'waterproof' te maken
Weblogposting








[Banners]


[Top events]




[Andere events]